Active Projects
Project Title | MSBU Approval | Approved Cost($) | Budget Account | Contractor | Est Completion | Payments | |
---|---|---|---|---|---|---|---|
Curacao Way/Southwind Drainage Basin: Upgrade Storm Water Drainage System (Phase II) More Details | April 10, 2018 | $ 46,222.00 | Okaloosa County, Friends of BWB, MSBU | October 31, 2022 | January 1, 2019 – $15,816 January 1, 2020 – $15,816 | ||
Woodlands Drive: Construct Sidewalk More Details | $ 31,288.20 | MSBU FY19-20 Future Spend | Okaloosa County | October 31, 2022 | |||
Hwy 20: Beautification of Medians – Lancaster Dr to Range Rd More Details | March 31, 2018 | $ 0 | FL Grant & DOT | BrightView | October 31, 2021 | ||
Range Road: Landscape Monument More Details | January 12, 2021 | $ 1,941.72 | MSBU Common Area | BrightView | |||
Chantilly Circle: North Entrance Beds* More Details | January 12, 2021 | $ 5,652.35 | MSBU Common Area | BrightView | |||
Oakmont Drive: Landscape Enhancement to Sign Bed* More Details | January 12, 2021 | $ 2,517.84 | MSBU Common Area | BrightView | |||
Winged Foot Drive: Landscape Entry Beds* More Details | January 12, 2021 | $ 2,884.13 | MSBU Common Area | BrightView | |||
Vine / Dead Plant Removal* More Details | February 9, 2021 | $ 7,200 | MSBU Tree Removal | BrightView | |||
Hwy 20: Enhance Landscape to Island located north of the Kangaroo Gas Station* More Details | February 9, 2021 | $ 893.62 | MSBU Common Area | BirghtView | |||
Hwy 20: Landscape Median Tips* More Details | February 9, 2021 | $ 4,421.34 | MSBU Common Area | BrightView | |||
Bay Dr / Bluewater Bay Blvd: Pump Inspection at Intersection More Details | October 13, 2020 | $ 165.00 | MSBU Irrigation | ||||
Simple Projects < $500 (FY 2020 / 2021) More Details | October 1, 2020 |