Project Overview


Vine / Dead Plant Removal*

MSBU ApprovalApproved Cost($)ContractorEst CompletionPaymentsCompletedFinal Cost
February 9, 2021$7,200BrightView


Description / Updates

Cut down vines along major roads and remove dead and unwanted plant material using Brush Cat, Sheers, Chain Saws and Pole Chain Saws. A request by Charlie Moore for clearing the vines along Woodlands Dr will be completed on this project.

Daily rate is $1800 for 3 people and equipment. Approved for 4 full days of work.

*Work completed in April / May 2021 – awaiting payment before changing status to Complete.

Below is the priority list by area for the vine removal:

1. Southwinds Traffic Circle
2. Bay Drive Entrance
3. Woodlands
4. Bay Drive (Past the entrance to the Tennis Court)

Anticipated start date is 16 April 2021.