Hwy 20: Landscape Median Tips*

MSBU Approval Approved Cost($) Contractor Est Completion Payments Completed Final Cost
February 9, 2021 $4,421.34 BrightView


Description / Updates

Install 275 Liriope & 95 Blue Daze plants and touch up pine straw to four Hwy 20 median tips.

*Work completed in May 2021 – awaiting payment before changing status to Complete.