Project Overview
Bay Dr / Bluewater Bay Blvd: Supplement Spring Pine Straw Application*
MSBU Approval | Approved Cost($) | Contractor | Est Completion | Payments | Completed | Final Cost |
---|---|---|---|---|---|---|
October 13, 2020 | $10,700 | BrightView | April 30, 2021 | June 30, 2021 – $10,725 | $10,725 |
Description / Updates
The Spring application was reduced to only 1,000 bales. In order to get it back up to where it needs to be, two full applications, the cost would be an additional $10,562.50 (for an additional 1,625 bales for Spring).
*Work completed in April 2021 – awaiting payment before changing status to Complete.