Bay Drive: Install Roadside Safety Posts with Reflectors
MSBU Approval | Approved Cost($) | Contractor | Est Completion | Payments | Completed | Final Cost |
---|---|---|---|---|---|---|
September 8, 2021 | $749 | November 1, 2020 | $743 |
Description / Updates
Installed in Nov 2020 for pedestrian safety from traffic at the curve. The marina and private citizens paid $750 and MSBU paid the other half. Total cost ~ $1,450.
The delayed billed was because the worker wanted to complete the job 100% and needed the wood to cure before painting.